CASE STUDY
Successful 16,000 GPM Emergency Sewer Bypass
SITUATION
Emergency sewer work 30 feet from the Don River in Toronto
APPROACH AND OUTCOMEs
Aquatech engineers and field technicians successfully engineered, delivered, installed, operated and continuously monitored an emergency sewer bypass pumping system with two 18” and two 12” diesel driven bypass pumps with remote live continuous monitoring/alerts on operating pumps, discharge flow rate, liquid level in manhole, piping system pressure and vacuum levels to optimize reliability, monitoring and efficiency. The discharge pipe consisted of 24” HDPE DR17 pipe to meet the friction loss
requirement as well as the City of Toronto bypass pumping specifications.
Aquatech offers full turn-key bypass solutions, engineered and supported with decades of experience
and best technology to support reliable results.